Who administers it
The City of Cheney, not Spokane County. Cheney operates its own publicly owned treatment works, so the county’s 30-day and 90-day clocks are not Cheney’s rule. The code establishes “a wastewater division of the city” inside the Public Works Department (CMC 15.04.010), run by the director of public works: “The director of public works, who shall be the director of the wastewater division” (15.04.020), and “Director means the director of public works and/or designee. The director is the person designated by the city to direct the operation of the POTW” (15.04.030).
Contacts as printed by the city: City Hall, 609 2nd Street, Cheney, WA 99004; Utilities 509-498-9209; Public Works Manager (509) 498-9322; after-hours utility emergencies 509-498-9230. Cheney publishes no separate FOG page, fee schedule or inspection form; questions about a grease interceptor go to Public Works.
What the code requires
The grease-interceptor section is CMC 15.04.067(b), quoted in full: “Grease, oil, and sand interceptors shall be provided when, in the opinion of the director, they are necessary for the proper handling of wastewater containing grease and oil in excess of the limits in the opinion of the director or excessive amounts of sand or other settle-able solids. Such interceptors shall not be required for domestic users. All interceptors shall be of type and capacity approved by the director and shall be located to be easily accessible for cleaning and inspection. Each user shall maintain, inspect, and clean required interceptors on a schedule that ensures they capture the intended pollutants, and prevents their reintroduction into the storm or sanitary sewer systems. Users shall bear all expenses related to installation, maintenance, and repair of interceptors, and the proper disposal of removed materials” (Ord. No. R-93, § 1(part), 1999).
Three things follow. There is no numeric interval and no 25% line in Cheney’s code; the standard is that the device keeps capturing grease and the grease does not get back into the sewer. Sizing is whatever “type and capacity” the director approves; the section cites no plumbing-code table. And the cost of disposal is yours, which is why the disposal manifest matters here as much as the pump-out.
Sizing, plans and the prohibited list
Pretreatment facilities “shall be provided, operated, and maintained at the user’s expense,” and “detailed plans showing the pretreatment facilities and operating procedures shall be submitted to the department and city for review and approval” (15.04.065(a)). The discharge the interceptor exists to prevent is spelled out in 15.04.051: “any solid or viscous substances including fats, oils, and greases in amounts which may cause obstruction to the flow in a POTW,” and separately “any incompatible substance such as: grease” or anything “greater than 0.5 inch in any dimension.”
Records: three years
Users “shall retain, and make readily available for inspection and copying, all records of information maintained to comply with this chapter” including “approved operations and maintenance procedures (inspections, lubrication, repair, etc.)” (15.04.073(a)), and “these records shall remain available for a period of at least three years,” longer during litigation or where the director requires it (15.04.073(c)).
Inspection and enforcement
“As a condition of receiving sewer service, the director shall have immediate access between the hours of 8:00 a.m. and 5:00 p.m., Monday through Sunday to all buildings or premises served by the POTW” (15.04.100), and refusing that access “shall be grounds for termination or suspension of wastewater treatment services” (15.04.100(4)). A violation draws a notice of violation stating “the violation, corrective measures, and other information necessary to remedy the violation” (15.04.120). After notice, “a maximum civil penalty of up to $1,000.00 per violation. Each day upon which a violation occurs or continues shall constitute a separate violation” (15.04.122(a)), plus “reasonable attorneys’ fees, court costs, and other expenses” of enforcement (15.04.122(b)). Any violation of the chapter is also “a gross misdemeanor” (15.04.121).
What we do not quote
The publisher’s code-currency date for the sections above, any Cheney standards manual or sizing policy beyond “type and capacity approved by the director,” and any FOG fee or inspection schedule, because the city publishes none. The City Clerk (509-498-9283) can tell you whether chapter 15.04 has been amended, and Public Works can tell you what the director currently expects of a particular kitchen.
How we service Cheney kitchens
Cheney’s standard is a result, so the evidence is a reading. On every visit we measure the grease and solids before pumping and write the percentage on the record; a device that stays under 25% between visits is demonstrably capturing what it should, and a device that does not gets a shorter interval. We plan at 20%. Kitchens that want one number usually adopt the Spokane County calendar — 30 days for traps, 90 for interceptors — as their house rule; it is not Cheney’s rule, but it is a schedule a director can read at a glance. The pump-out is full, not a skim: pumped dry, baffles and tees washed, wash water hauled away, and a manifest showing the “proper disposal of removed materials” the code charges to you. Same truck that runs Spokane and the Valley; EWU-adjacent restaurants, First Street, the Betz Road and Cheney–Spokane Road corridors are all on the route.
Cheney kitchens, on a schedule you can show
Device size and address. The first reading sets the interval.